11. Which of the following statements does not describe iterative assessment?
  • Provides insight into the technical progress of the project.
  • Is optional and often eliminated during early iterations.
  • Can result in updates to the plan for the subsequent iteration.
  • Includes a comparison of the iteration plan with the actual cost, schedule, and content accomplished.
Correct Answer: B

12. Which of the following statements is false concerning the development case?
  • It tells you which artifacts to produce.
  • You can use it to specify the tools used to produce an artifact.
  • You can use it to specify the degree of formality associated with an artifact.
  • It is fixed during Inception and does not generally change over the course of a project.
Correct Answer: D

13. Which of the following does not relate to project planning for iterative development?
  • Produces a coarse-grained plan identifying the number of iterations per phase, their objectives, and duration.
  • At the most detailed level, consists of an iteration plan establishing the fine-grained activities and milestones for each iteration.
  • Incorporates risk management.
  • Drives to details for complete plan by end of Inception
Correct Answer: D

14. Which of the following statements does not characterize a typical iteration in the Elaboration phase?
  • Involves more analysis and design than testing effort.
  • Updates the risk list.
  • Contributes significantly to the Software Architecture Document.
  • Spends a significant amount of effort in developing the vision and business case.
  • Requires the leadership of the software architect.
Correct Answer: D

15. Which of the following statements regarding requirements is true?
  • Only external requests for change need to be approved by the change review team.
  • To avoid confusion, all requirements should be standalone with no links to other requirements.
  • Requirements attributes eliminate the need for configuration and change management of requirements.
  • Traceability links and requirements attributes are useful in impact assessment of proposed changes.
Correct Answer: D

1 comment:

Unknown said...

Hi

I read this post 2 times. It is very useful.

Pls try to keep posting.

Let me show other source that may be good for community.

Source: Process management interview questions

Best regards
Jonathan.

 

© blogger templates 3 column | Make Money Online